builderbill

Graphical Construction Glossary >> Concrete and Concreting. >> >> Strip Footing


Strip Footing
A footing that is longer in one direction than the other. Typically under walls.
Starter Bars
Steel reinforcing bars cast into two separate pours of concrete. With lap joints to main bars they continue the reinforcement through the concrete joint.
Back-fill
The fill material or the process of filling and compacting excavations when the work has been completed.



a sketch of a strip footing for a cmu wall

reinforced concrete strip footing

This type of footing has the advantage that it can be stepped in brickwork or blockwork increments so that it can easily be adapted to sloping sites.

Above is a sectional detail of reinforced concrete footing showing some of the requirements for the design. Any drawing like this only tells part of the story. The specifications will also details like:-

  • Stripping off the vegetation and topsoil layer.
  • The minimum bearing capacity of the subgrade.
  • The compaction of the fill inside the building and the back-fill outside.
  • The strength of the concrete and the corefill.

The contract specifications in their turn will call up regulatory standards like and building codes that the concrete, the reinforcing steel, the vapour barrier, the termite protection method etc etc.

starter bars in a strip footing

The photo above shows a strip foundation that has been poured with the starter bars easily seen. Often 12mm starter bars used to be seen with a hook on the end in situations like this.

Partly it was a hangover from the days when hooks were used in plain bars to provide grip for the concrete but with the use of deformed bars and correct laps there is now no need for them structurally, but they were still used for safety reasons. Imagine someone falling onto them.

Now with the use of these cheap plastic caps the hooks can be left off and the bars are still safe.

concrete blocks laid on strip footings

Blocks starting to be laid on a job similar to the one in the sketch at the top of the page.

When all the blocks are laid to the slab height they are corefilled BEFORE BACK-FILLING. Washed sand is used and it is watered in which can achieve good compaction. Care should be used with mechanical compaction equipment not to damage the blockwork.

N12 starter bars

A bundle of N12 starter bars to b e used in reinforced blockwork construction.



If you didn't find exactly what you are looking for try this search tool that will search the site and the web.


"What can be added to the happiness of a man who is in health, out of debt, and has a clear conscience?
Adam Smith 1723-1790


"When we build, let us think that we build for ever."John Ruskin 1819-1900


coates hire
Hire Equipment
hafele
Furniture Fittings - Architectural Hardware - Electronic Locking Systems - Technical Hardware
BuilderBill sponsorship

BuilderBill Books


building maths
Building Maths

Stair Design
asbestos ebook
Asbestos Book

Calculator Pages.

Concrete yardage calculator

Reader's Questions.

Questions and answers.


 

 



Please Note! The information on this site is offered as a guide only!  When we are talking about areas where building regulations or safety regulations could exist,the information here could be wrong for your area.  It could be out of date!  Regulations breed faster than rabbits!
You must check your own local conditions.
Copyright © Bill Bradley 2007-2012. All rights reserved.
Page copy protected against web site content infringement by Copyscape